New Energy Rules are changing what U.S. data center developers must establish before they can commit to a construction schedule. New York paused certain approvals for new hyperscale projects, while Texas moved a financial commitment ahead of utility interconnection studies for large loads. Federal permitting proposals could change parts of the review process, but they do not remove either state-level obligation. The business question is no longer just how much a campus will pay for electricity once it opens. It is how much money the developer must commit before it knows when the site can receive power and whether it can secure the permits it needs.
New Energy Rules Reshape State Approvals
On July 14, 2026, New York Governor Kathy Hochul signed Executive Order 62, imposing a one-year moratorium on new hyperscale data center construction. The order suspended affected discretionary state permits that had not already been deemed complete while the state develops stricter environmental and grid standards. Projects using at least 50 megawatts (MW) and those with pending Department of Environmental Conservation applications face particular exposure. For a developer, the practical distinction is between an application that has been filed and one the state has deemed complete. Filing alone does not settle whether the pause applies.
The order also put power sourcing and ratepayer protection into the same decision. Under New York’s framework, affected data centers are to supply their own power or pay more for energy. That is a choice between different project costs and obligations, not evidence that either route will be available on the developer’s preferred schedule. A power plan must account for the cost of supply, while the permit review determines whether the proposed facility can proceed. Resolving one does not establish the result of the other, and the research does not quantify the added energy charges.
Virginia introduced its Data Center Accountability Framework in September 2026, tightening environmental, commercial, and zoning scrutiny. That differs from New York’s pause and from the Texas rule that places financial security before an interconnection study. The differences matter when screening sites: a state without the same megawatt threshold can still present a difficult approval path. For each parcel, the useful comparison is which approval or payment comes first, what evidence is needed to clear it, and which costs the developer would incur while the decision is pending.
| State | Measure | Early Project Question |
|---|---|---|
| New York | One-year hyperscale moratorium under Executive Order 62 | Was the affected discretionary permit application deemed complete? |
| Texas | Interconnection security for requests of at least 75 MW, separate from the permit suspension directive | Can the developer post security before studies begin? |
| Virginia | Data Center Accountability Framework | What environmental, commercial, and zoning scrutiny applies to the parcel? |
Texas Moves Grid Costs Earlier
New Energy Rules Put Security Before Studies
Texas adopted 16 Texas Administrative Code § 25.194 on September 18, 2026, to implement Senate Bill 6. The rule took effect on October 8, 2026, and requires large loads of at least 75 MW to provide financial security and contribute to interconnection costs. It also provides for standardized large-load interconnection agreements. The timing matters as much as the threshold: the developer must post security before the interconnection study can begin, rather than waiting for that study to clarify what work the connection will require.
At $50,000 per MW of requested capacity, a 75 MW request requires $3.75 million in financial security before studies begin. That figure is not an estimate of the final grid upgrade bill, and it should not be entered into a budget as though it were one. The rule also requires cost contributions, so the early security and the eventual connection cost are separate planning questions. The distinction is especially relevant when a developer is still comparing sites and has not decided which project to build. The related analysis of data center cost risk examines why the timing of those commitments matters.
Texas created a separate permitting issue on September 21, 2026, when Governor Greg Abbott directed the Texas Commission on Environmental Quality to suspend issuance of data center permits pending grid and water audits by ERCOT and the Texas Water Development Board. Posting security for a grid study does not clear a permit affected by that directive. Nor does progress on an environmental application establish that the utility can serve the requested load. The available record does not establish when the audit-related suspension ended or whether it was lifted by November 23, 2026. A project schedule therefore needs separate assumptions for the two processes.
Federal Proposals Address Different Permits

Faster Review Does Not Provide Power
The Associated Press reported a bipartisan Senate deal on the Bipartisan American Affordability and Jobs Act of 2026, a permitting bill intended to speed energy infrastructure approvals. The proposal would shorten federal review timelines under laws such as the National Environmental Policy Act, limit challenges, and make data centers liable for the electricity they use. A Senate deal does not establish enactment or an effective date. The potential schedule benefit applies to a project that needs the federal review in question, not automatically to every data center that might draw power from new infrastructure.
The Environmental Protection Agency was also considering a separate change to Clean Air Act minor-source permitting. As reported in August 2026, the proposal would give states discretion to drop public notice and hearing requirements for certain air permits relevant to data centers. It faced public and legal opposition, and the available record does not show that it became final by November 23, 2026. The distinction is procedural: a change to notice or hearings would not, on its own, establish that a particular on-site power proposal qualifies for a minor-source permit or that the facility has secured every required approval.
The federal and state measures can affect the same development without answering the same question. A shorter federal review could matter for an energy project that would serve a campus, while the campus itself could still face a state permit hold or an incomplete grid study. Similarly, the potential for a different air permit process does not tell a developer whether on-site generation would satisfy New York’s power framework. The practical step is to identify which approval actually controls the date that power can be delivered, then distinguish adopted requirements from proposals that cannot yet support a firm schedule.
Data Center Siting Under New Energy Rules
Cleanview reported a 28% decline in data center construction starts in the third quarter of 2026, the first quarterly decline since early 2025. That figure records a slowdown in starts, not the share of projects stopped by regulation. It does not isolate the effect of permit pauses, interconnection costs, or any other factor. In particular, Texas’s financial security rule took effect on October 8, 2026, after the quarter ended. The starts figure therefore cannot measure the effect of an operating rule that was not yet in force during the period.
For a developer comparing parcels, the order of commitments can matter as much as the final price of power. In New York, the first question may be whether the permit file was deemed complete before the pause applied. In Texas, it may be whether the developer is prepared to post security before knowing the study result. Where water or zoning review is unresolved, the power schedule should not substitute for a separate approval estimate. For readers interested in exploring more about technology developments, Camp Tech Wise provides insightful coverage within our network.
A site comparison should identify when the developer expects to post security, when each permit decision is needed, and which expenditures the project can defer if either date slips. The power plan should also match the capacity the developer is requesting, rather than assuming a site can support a later buildout on the original terms. The available evidence supports changes in the timing and allocation of project risk, but not a reliable estimate of how many campuses will move to another state. A site with lower projected electricity costs can still be the harder project to deliver if its grid or permit schedule is less certain.